Post Office Redevelopment Process

(dates based on Maplewood Patch)

REMAINING STEPS (items with * include public comment periods)
PHASE ACTIVITY DATE PURPOSE
BUILDING Letters of Interest Summer 2013 Township Committee will ask developers whether they are interested and request information on qualifications and design ideas.
Requests for Proposals Fall 2013 Township has indicated that proposals will be reviewed without public comment during a roughly 90-day period toward the end of the year. Stated goal is to choose a proposal and developer by the end of 2013.
US Post Office closes November 2013 US Post Office lease expires.
Implementation TBD—early 2014? Township sells land to developer, signs development agreement. Development plans submitted to Planning Board and Construction office for approval.
Related documents can be found here.   Explanation of terms.
This schedule and other information can be found here:

Completed Steps